Published in the April 9, 2010 Sandy, Buckhead and Brookhaven Reporter Newspapers.
In about 18 months, drivers will be able to get on and off Ga. 400 between exits 4 and 5.
Georgia Department of Transportation crews are working on the half-diamond interchange at Hammond Drive and Ga. 400.
The $18.2 million project began in February 2009 and should be completed by August 31, 2011, according to transportation department spokesman Mark McKinnon.
The half-diamond interchange, named for how it looks from above as it connects the two roads, will provide a new exit off of Ga. 400 in hopes of reducing traffic congestion. The project, which has been in the works for 15 years, will build entrance and exit ramps from Hammond Drive to Ga. 400 and widen the bridge over the highway on Hammond Drive from four lanes to nine lanes.
McKinnon said clearing for the interchange project was complete. Utility relocation will continue so crews can build retaining walls and begin a portion of the new bridge on the north side of Hammond Drive.
The state is funding the project. The Perimeter Community Improvement District (PCID) and the city of Sandy Springs also have contributed money, according to information published in February on the city of Sandy Springs’ Web site.